WHPC Report
Dave Wood, 6/10/22
A couple of updates as it’s not been long since my last report.
Road Surfacing
B&NES have booked w/c 7th November to resurface through West Harptree as per the attached plan. The blue area shows the extents. Likely to be 4 days of resurfacing followed by a days lining. This date has been coordinated to follow on from two weeks of BT works that conclude the week prior.
They will shortly put up advance warning signs and do a letter drop.
Speeding Phase 2 Meeting
Following conversion with Philip I have asked the Head of Highways to nominate the most appropriate highways officer to attend on the 31/10/22 meeting